Wednesday, June 20, 2012

Bridge Building Over High Beck

Last week saw us on two work parties starting the mammoth job of rebuilding the bridge on the Liza path over High Beck.  This job was made harder by the huge quantity of midges, even the National Park & Forestry staff said they had never known as many in one place.

The helicopter had delivered the materials a few weeks ago all we had to do was assemble them (and a bit more).

The abutment on one side had been washed away so the first job was to dig out new foundations & collect a lot of stone to build with.

DSCF4475

Large stones were used as the facings for the abutment with smaller ones as infill

DSCF4476DSCF4477

Andy was collecting stones whilst Karen helped build the abutment, it was very similar principles to dry stone walling, although we were using a little concrete to hold some of the stones in place

DSCF4478DSCF4479DSCF4480DSCF4482

It takes  plenty of deliberation over which stones fit best where

DSCF4483

Andy busy mixing the concrete.

DSCF4484

At the end of Tuesday the abutment was almost complete, we needed to raise it about 3inches & fill the middle with concrete.

DSCF4485

So Thursday we were back on it, thankfully there was a little breeze & only a few midges.

DSCF4486

The abutment was finished, now the small matter of moving the beams onto it.  The beams were 11m x 36cm x 23cm so not light

DSCF4492DSCF4493

Using cantilever principles & some good old brute force the beams were slowly lifted into place

DSCF4494DSCF4495DSCF4496DSCF4498

Using the lats from the old bridge as a rest slowly the beams are lifted higher as more are inserted

DSCF4501

And finally the first beam is rested on both abutments

DSCF4502

It’s tiring work.

DSCF4503DSCF4504

Then its time to start on the second beam, Andy, Angus & Julian act as a counter weight as the beam is moved into place

DSCF4505DSCF4506

 

Once the beam is on both abutments the last job is to roll the beam over

 

Job done, it’s been a hard but rewarding two days work

DSCF4514

Although the beam is not in its final position & it doesn’t actually matter if its not completely level we haven’t done badly that’s 3.3degrees off level.

DSCF4515

There are a few more work parties needed to paint & assemble the final bridge.

No comments: